Photovoltaic plant, agrivoltaics, grid connection and CoRDiS

Energy infrastructure lawyer Paris: solar permits, grid connection.

Ground-mounted photovoltaic plant, solar carports, agrivoltaic project or municipal solar farm: before the first production, the project goes through a planning authorisation, sometimes an environmental derogation, and then a connection procedure to the public grid. Each of these stages has its own rules, its own court and its own time limits. An energy infrastructure lawyer in Paris therefore reviews them one stage at a time.

A challenge to a dispute-settlement decision of the CoRDiS, the dispute settlement committee of the Energy Regulatory Commission, must be brought within one month before the Paris Court of Appeal, and a challenge to a permit within two months. Keep the notification and display dates as soon as you receive them.

Solar energy · Paris

Get a first analysis

Send the permit application or the decision received, the extracts of the local urban plan (plan local d'urbanisme), the agricultural or environmental study, the connection proposal and the exchanges with the grid operator: the firm examines the blocking stage and the legal route available.

24 à 48 h

first legal
review

€80incl. VAT

Preliminary review of your case. Examination of your documents and a first written analysis by Reda Kohen, within 24 to 48 business hours. Payment is made online after this form is sent.

  • Up to 1 GB of documents, folders and subfolders accepted
  • Secure payment, no banking data stored
  • Terms and fee agreement

Click or drag your files here
All formats accepted (PDF, Word, images, etc.)

Sending...

Payment constitutes a request for immediate performance of your analysis. Your data is used only to process your request. Terms · Privacy policy.

In the media

  • Lexbase

Kohen Avocats, Paris 17

Solar project: what determines authorisation and grid connection

Reda Kohen, lawyer at the Paris Bar
Reda KohenLawyer at the Paris Bar

Public law · Paris 17th arrondissement

What an energy infrastructure lawyer in Paris does

  • Paris Bar
  • Public law
  • Planning and energy

Reda Kohen, avocat at the Paris Bar, can act for solar project developers, landowners, farmers and municipalities, on the authorisations for a photovoltaic project and on its connection to the public electricity grid.

A solar project is not judged on a single rule. The firm checks, in order, the planning regime that applies according to capacity, compatibility with agricultural, natural or coastal zoning, any protected-species derogation, and then the technical and financial conditions of the connection.

Disputes do not all go to the same court. The permit and the derogation are challenged before the administrative courts, whereas a dispute with Enedis or RTE over access to the grid goes to the dispute settlement committee of the Energy Regulatory Commission, and then to the Paris Court of Appeal.

Send what you have, even if incomplete: the firm will prioritise and complete the file with you. In an emergency, call +33 6 46 60 58 22.

Official profile in the directory of French lawyers (CNB)Firm at 11 rue Margueritte, 75017 Paris

The right planning route

Peak capacity, ground-mounted or carport installation and height determine whether the project is exempt, requires a prior declaration or a building permit, and which authority is competent.

The land and its protections

Agricultural zones, the departmental framework document, coastal municipalities and protected species each require a distinct demonstration, which must be prepared from the application stage.

The grid and its regulator

The connection contribution, the share under the regional scheme and the conditions of access are discussed with the operator, and then before the CoRDiS when the disagreement persists.

The rules

Planning, environment, grid: the applicable rules

Four sets of rules govern the authorisation and connection of a solar project.

  1. Outside remarkable heritage sites, the surroundings of listed historic monuments and classified sites, ground-mounted solar structures and carports of less than three kilowatt-peak and no more than one metre eighty high are exempt from any formality (Article R*421-2 of the French Planning Code). Under this ordinary regime, a prior declaration is sufficient below three kilowatt-peak above one metre eighty, and from three kilowatt-peak up to less than three megawatts (Article R421-9, h), and a building permit is required from three megawatts (Article R421-1). In the protected areas, a prior declaration is sufficient only below three kilowatt-peak (Article R421-11, I, b), and a permit is in principle required above that. The prefect is competent where the energy is not mainly intended for the applicant and for projects presented as agrivoltaic (Article R*422-2).
  2. In an agricultural, natural or forest zone, the installation must not be incompatible with the agricultural activity of the land nor harm landscapes (Article L151-11 of the French Planning Code). This compatibility is assessed at the level of contiguous plots belonging to the same farm, and outside agrivoltaics no solar structure may be built outside the areas of the departmental framework document (Article L111-29). For an application filed in 2022, before this scheme, the Toulouse Administrative Court of Appeal annulled a refusal based on the absence of significant agricultural activity, in view of a genuinely organised sheep farm (CAA Toulouse, 17 April 2025, No. 24TL02067).
  3. Where the site shelters protected species, the derogation requires the absence of any other satisfactory solution, the maintenance of the populations and an imperative reason of overriding public interest (Article L411-2 of the French Environmental Code). Renewable energy projects and their connection works are deemed to meet that requirement when they satisfy the conditions set by decree (Article L211-2-1 of the French Energy Code). The Council of State (Conseil d'État) held that a site outside the municipality was not an alternative to the municipal project of Cruis (CE, 7 May 2026, No. 496357).
  4. Connection comprises extension, service-connection or reinforcement works, which form part of the public networks (Article L342-1 of the French Energy Code), and the regional renewable energy connection scheme sets a pooled unit share (Article L342-3). The articles of the Energy Code, in their wording then applicable, "require only that the connection form part of a Regional Scheme and not that it fall within the pooling perimeter defined by it" (Cass. com., 6 April 2022, No. 20-23.163) (our translation). A disagreement over access to the grid may be referred to the CoRDiS (Article L134-19).

A permit does not guarantee either the connection or its cost: the grid operator's proposal must be examined as soon as it is received, because it often determines the economic balance of the project.

Your documents

What to send depending on the blocked stage

The file is rebuilt from the administrative acts, the studies and the exchanges with the grid operator.

Position A

Your authorisation is refused or challenged

  • Permit application or prior declaration, with the notice, the plans and the declared peak capacity
  • Decision refusing, deferring or granting the permit, with the notification and display dates
  • Extracts of the local urban plan, the departmental framework document and the opinion of the competent commission
  • Agricultural study, impact assessment, wildlife surveys and any derogation application

Position B

Your connection is blocked or challenged

  • Complete connection application, acknowledgement of receipt and technical and financial proposal received
  • Connection agreement, grid injection access contract and special conditions
  • Calculation of the contribution, amount of the regional share and applicable regional scheme
  • Exchanges with Enedis, RTE or the local distribution authority, notices of works and records of outages

Do not let the period for accepting the connection proposal expire during an informal discussion: set out your reservations in writing and keep proof that they were sent.

The firm also handles:

  • Administrative court
  • Administrative law
  • Local authorities
  • Public law

The method

How the firm examines your project

Identifying the blocking stage, the applicable text and the competent court before taking any step.

Step 1

Reading the file and the dates

The firm notes the capacity, the location, the zoning, the decisions received and their notification dates, so as to establish at once the time limits still open.

Step 2

Identifying the applicable regime

Planning authorisation, the prefect's competence, the agricultural framework document, the Coastal Act, the protected-species derogation or a connection dispute: each question is given its exact legal basis.

Step 3

Administrative appeal or negotiation

Depending on the case, the firm prepares an informal administrative appeal, a new and better-supported application, a regularisation measure or a reasoned complaint to the grid operator.

Step 4

Going to court or to the regulator

If the blockage persists, the firm may bring the matter before the competent administrative court or administrative court of appeal, or the CoRDiS, and then follow the challenge before the Paris Court of Appeal.

Jurisdiction changed for acts taken from 1 July 2026 concerning plants of at least five megawatts, earlier acts remaining subject to the former regime: checking the date of the act and the court of first instance is part of the initial analysis.

The timetable

The stages of a solar project

From securing the land to commissioning, each stage opens its own challenges.

  1. Securing the land

    Before any application. Promise of lease, long-term emphyteutic lease or occupancy agreement: the term, the conditions precedent and the allocation of responsibilities are fixed at this stage.

  2. Studies and file

    The agricultural study, the environmental assessment depending on the project, surveys and zoning analysis prepare a complete and consistent application.

  3. Examination and decision

    The prior declaration or permit is examined, often by State services, with the opinions of the departmental commissions concerned.

  4. Grid connection

    The complete application triggers the operator's proposal, followed by the connection agreement and the grid access contract.

  5. Challenges and commissioning

    Third parties have two months from the first day of a continuous two-month period of regular display on the land, and the court may, under certain conditions, stay its ruling to allow a regularisation.

The checks

What the firm checks before acting

Each argument must rest on an identified document, date and text.

  • Peak capacity and location: exemption, prior declaration or permit, and the authority competent to decide.
  • Zoning of the land: local urban plan rules, departmental framework document, coastal municipality and eligible brownfield sites.
  • Wildlife issues: surveys, avoidance and reduction measures, and whether a protected-species derogation is really needed.
  • Connection: completeness of the application, costed contribution, share under the regional scheme and clauses of the access contract.
  • Time limits and court: notification date, time limit to challenge, court of first instance and route before the Paris Court of Appeal.

Summary

Situation, evidence, response

Six common situations and the first priority in each.

Situation

Ground-mounted plant refused in an agricultural zone

Decisive evidence: Agricultural study, costed farm plan, agreement with the farmer and soil characteristics.

Time limit: Two months from notification of the refusal.

Useful action: Informal administrative appeal or court challenge showing significant agricultural activity, or a new, better-supported application.

Situation

Agrivoltaic project in preparation

Decisive evidence: Services provided to the plot, main agricultural production, reversibility and the farmer's income.

Time limit: Before filing, as the classification determines the competent authority.

Useful action: Check the criteria of Article L314-36 and of the decree of 8 April 2024 before presenting the project.

Situation

Solar farm in a coastal municipality

Decisive evidence: Location plan, density of neighbouring urban development, any brownfield status.

Time limit: From the preliminary design stage, as continuity determines feasibility.

Useful action: Show continuity with an urbanised area or examine the derogation specific to brownfield sites.

Situation

Protected species on the site

Decisive evidence: Surveys, alternatives studied, avoidance, reduction and monitoring measures.

Time limit: Before the application, to decide whether a derogation is required.

Useful action: Document the alternatives against the project's objectives and the imperative reason of overriding public interest.

Situation

Share or contribution disputed

Decisive evidence: Connection proposal, applicable regional scheme, detail of the works invoiced.

Time limit: Written reservations before acceptance, then referral to the CoRDiS if necessary.

Useful action: Check the link to the scheme and the calculation, without waiting for commissioning.

Situation

Outages imposed by the operator

Decisive evidence: Grid injection access contract, special conditions, notices of works and production losses.

Time limit: According to the applicable limitation period, which runs from the day the facts enabling action were known or should have been known.

Useful action: Compare each outage with the commitments in the contract, then claim compensation.

Frequently asked questions

Your questions: energy law

What planning authorisation is needed for a ground-mounted photovoltaic plant?

The regime depends first on peak capacity and location. Ground-mounted solar structures and carports of less than three kilowatt-peak, with a height not exceeding one metre eighty, are exempt from any formality, except in a remarkable heritage site, in the surroundings of a listed historic monument or in a classified site (Article R*421-2 of the Planning Code). Under the ordinary regime, a prior declaration is required for structures of less than three kilowatt-peak that exceed one metre eighty, and for those from three kilowatt-peak to less than three megawatts, whatever their height (Article R421-9, h). From three megawatts, the principle of the building permit applies (Article R421-1). In a remarkable heritage site, in the surroundings of a listed historic monument or in a classified site, these thresholds do not apply: a prior declaration covers only structures of less than three kilowatt-peak (Article R421-11, I, b), and a permit is in principle necessary above that. These thresholds result from the wording in force since 16 November 2024, which must be checked at the date of filing. An installation placed on an existing roof calls for a different analysis, which is not covered here. The planning authorisation does not exhaust the authorisations required: depending on the project, an environmental assessment, a protected-species derogation or land clearance may be added. The firm therefore checks the declared capacity, the height, the location and the protections of the site before choosing the procedure.

The mayor or the prefect: who decides on a solar project?

In a municipality with a local urban plan, the mayor in principle issues planning authorisations on behalf of the municipality (Article L422-1 of the Planning Code). The Code nevertheless reserves several categories of projects to the prefect. The prefect is competent for facilities producing, transmitting, distributing and storing energy where that energy is not mainly intended for direct use by the applicant (Article R*422-2, b, of the Planning Code). A plant that feeds its output into the public grid therefore most often falls within the prefect's competence. The same article gives the prefect the installations presented by the applicant as agrivoltaic within the meaning of the Energy Code, since the wording in force on 7 July 2024. Conversely, an installation mainly for self-consumption may fall within the mayor's competence. This allocation has practical consequences: the authority that signs the decision, the department that examines the file, the opinions sought and the person to whom an informal administrative appeal is addressed. An error as to the competent authority may render the decision unlawful for lack of competence. The firm identifies the competent authority from the real use of the electricity produced and the classification given to the project.

Can a solar plant be installed on agricultural land?

It is possible, but under strict conditions. In an agricultural, natural or forest zone, the local urban plan regulations may allow installations necessary for public facilities that are not incompatible with the agricultural activity of the land and do not harm landscapes (Article L151-11 of the Planning Code). Since the law of 10 March 2023, this compatibility is assessed at the level of contiguous plots of the same farm, and no solar structure, outside agrivoltaics, may be built outside the areas identified by the prefectoral framework document (Article L111-29). The corresponding regulatory rules apply only to applications filed from one month after publication of the department's framework document (Article 8 of Decree No. 2024-318 of 8 April 2024): the filing date therefore fixes the regime applicable to the file. The administrative court examines the projected agricultural activity in concrete terms. For an application filed on 1 August 2022, the Toulouse Administrative Court of Appeal annulled a permit refusal for a 9.9 megawatt-peak plant, holding that an organised sheep farm, with a building, paddocks and an agreement with a breeder, was not limited to maintaining the site; it ordered the prefect to issue the permit (CAA Toulouse, 17 April 2025, No. 24TL02067). This is a decision on its own facts: the file must demonstrate the area, the footprint, the nature of the soils, local uses and the reality of the activity.

What is an agrivoltaic installation within the meaning of the law?

An agrivoltaic installation is a solar installation whose modules, located on an agricultural plot, contribute lastingly to the establishment, maintenance or development of agricultural production (Article L314-36 of the Energy Code). It must directly provide the plot with at least one service: improving agronomic potential, adapting to climate change, protection against hazards or animal welfare. It must also guarantee an active farmer significant agricultural production and a lasting income. It loses this classification if it causes substantial harm to one of these services or limited harm to two of them, if agricultural production is no longer the main activity of the plot or if the installation is not reversible. The plot taken into account is the continuous perimeter of the panels with the same agricultural characteristics (Article R314-108). The Council of State rejected the Confédération paysanne's challenge to the decree of 8 April 2024, specifying that the agronomic service requires two cumulative criteria, the agronomic quality of the soil and yield (CE, 16 March 2026, No. 494941). The firm checks each criterion before filing, because the agrivoltaic classification also changes the competent authority.

Is a photovoltaic farm possible in a coastal municipality?

In a coastal municipality, urbanisation is extended in continuity with existing towns and villages (Article L121-8 of the Planning Code). The Council of State holds that installing photovoltaic panels constitutes an extension of urbanisation within the meaning of this provision, and can therefore be authorised only in continuity with an area already urbanised, characterised by a significant number and density of buildings. In the Narbonne case, it set aside for distortion the judgment that had annulled the permit, although the land adjoined a large built-up industrial zone, and referred the case back to the court (CE, 17 February 2023, No. 452346). Since 12 March 2023, a derogation allows solar structures to be authorised on certain brownfield sites listed by decree (Article L121-12-1). The authorisation then falls to the State, after the opinion of the departmental commission for nature, landscapes and sites. The applicant must also show that the project is preferable, for reasons of general interest, to a technically feasible renaturation. The firm therefore begins by placing the land in relation to existing urbanisation.

When is a protected-species derogation needed for a solar project?

Destroying or disturbing protected species and their habitats is prohibited, unless a derogation is granted. This requires three cumulative conditions: the absence of any other satisfactory solution, the maintenance of the populations in a favourable conservation status and one of the grounds provided for, including an imperative reason of overriding public interest (Article L411-2 of the Environmental Code). Renewable energy projects and their connection works are deemed to meet this reason when they satisfy the conditions set by decree; the existence of an acceleration zone does not, by itself, constitute another satisfactory solution (Article L211-2-1 of the Energy Code). In its version in force since 19 August 2026, the Code specifies that the derogation is not required where sufficiently guaranteed avoidance and reduction measures make the risk insufficiently characterised, with a monitoring system (Article L411-2-1). For a 10.66 megawatt-peak farm, the Council of State assessed the alternative solutions against the objectives specific to the municipal project and recognised the imperative reason of overriding public interest (CE, 7 May 2026, No. 496357). The firm first examines the surveys and the alternatives studied.

How can the connection cost or the regional share be challenged?

Connection comprises, as the case may be, the creation of extension or service-connection works and the reinforcement of existing networks (Article L342-1 of the Energy Code). The regional renewable energy grid connection scheme defines the works to be created and a unit share approved by the State (Article L342-3). The Court of Cassation held that the provisions, in their wording then applicable, "require only that the connection form part of a Regional Scheme and not that it fall within the pooling perimeter defined by it" (Cass. com., 6 April 2022, No. 20-23.163) (our translation). This outcome is unfavourable to the producer who claimed to escape the share because it did not directly benefit from the pooled works. The Paris Court of Appeal applied it, recalling that "the obligation to pay the share is subject to the dual condition that the connection" serves a renewable installation and forms part of a regional scheme (our translation); it reformed the CoRDiS decision and held the producer liable (CA Paris, pôle 5 ch. 7, 18 January 2024, No. 20/05171). A challenge remains worthwhile on other grounds: scope of the dedicated works, accuracy of the calculation, scheme applicable at the date of the application. The firm checks these points before the proposal is accepted.

What can be done if there is a disagreement with Enedis or RTE over grid access?

The dispute settlement committee of the Energy Regulatory Commission, the CoRDiS, may be seized of a dispute between a public network operator and a user, in particular in case of refusal of access or disagreement over the conclusion, interpretation or performance of contracts; the limitation rules of the Civil Code apply to such claims (Article L134-19 of the Energy Code). The committee in principle rules within two months, extended to four months if documents are requested, and its decision may carry periodic penalty payments (Article L134-20). At the request of the party bringing the matter, it may take effect from a date before the referral, but not earlier than the first formal challenge raised by one of the parties, nor more than two years before the referral. The Court of Cassation approved an order requiring RTE to conclude a connection agreement, holding that the CoRDiS "has, in carrying out its dispute-settlement mission, the power to impose requirements and orders affecting the conclusion, content or performance of agreements" (Cass. com., 19 June 2019, No. 17-20.269) (our translation). A written, documented complaint to the operator usefully precedes the referral, because it fixes the date of the challenge and the scope of the dispute.

What is the time limit to challenge a CoRDiS decision?

CoRDiS decisions in dispute settlement are challenged before the Paris Court of Appeal (Article L134-24 of the Energy Code). The challenge is brought within one month, by written declaration filed with the court registry; on pain of inadmissibility raised by the court of its own motion, the declaration states its purpose and contains a summary statement of the grounds, the full statement having to be filed within the following month (Article R134-22). This is not an ordinary appeal. The Court of Cassation approved the court of appeal for holding that "CoRDiS decisions may be challenged only by the specific challenge that the above provisions provide for", and held inadmissible the claims of a company that had merely submitted observations out of time (Cass. com., 16 March 2022, No. 20-16.257) (our translation). This formal requirement is strict: a party that wishes to obtain the reformation of a decision must itself bring its challenge. The president of the CoRDiS may submit observations and appeal to the Court of Cassation against the judgment that annuls or reforms the decision. The firm calculates the time limit from notification and prepares the declaration and the statement of grounds in parallel.

Does a delay in connecting a plant give a right to compensation?

The answer depends on the harm claimed, and the case law on the December 2010 moratorium is unfavourable to producers. The decree of 9 December 2010 suspended the obligation to purchase photovoltaic electricity, and many project developers complained that the grid operator had processed their application too slowly. The Court of Cassation held that the purchase obligation arising from the order of 12 January 2010 constituted State aid not notified to the European Commission, so that the claimants could not rely on the loss of a chance to benefit from it, "such harm not being recoverable" (Cass. com., 18 September 2019, No. 18-12.601) (our translation). The Montpellier Court of Appeal upheld the dismissal of a comparable claim, holding that "the harm of losing the chance to benefit from a tariff arising from this unlawful State aid is not recoverable damage, whatever the basis of liability relied on" (CA Montpellier, ch. com., 24 March 2026, No. 24/05823) (our translation). These decisions concern the loss of a tariff arising from that aid; they do not, on their own, decide every other head of loss. The firm therefore examines the exact nature of the damage, the applicable contract and limitation before claiming compensation.

Do grid outages for works engage the operator's liability?

A producer connected to the public distribution grid signs a grid injection access contract, whose general conditions govern outages. In the contracts examined by the Court of Cassation, the operator undertook to limit outages for works to two per calendar year, of less than eight hours in total, with fifteen days' notice. A court of appeal had ruled out Enedis's liability by linking the renewal of primary substations to the heavy maintenance clause. The Court of Cassation set that judgment aside for breach of the binding force of the contract, on the ground that "Articles 5.1.1.1 and 5.1.1.1.1 of the general conditions did not provide for any condition relating to the scale of the renewal works", and that these works were not listed in the special conditions (Cass. com., 18 March 2026, No. 25-13.293) (our translation). The case concerned wind farms, but the reasoning bears on how the access contract is read. The outcome therefore depends on the precise wording of the general and special conditions signed. The firm compares each outage, its notification and its duration with the contractual commitments, then quantifies the production losses before any claim.

Which court and what time limit to challenge the permit of a solar plant?

An action for annulment for abuse of power (recours pour excès de pouvoir) is brought within two months (Article R421-1 of the Code of Administrative Justice), which runs against third parties from the first day of a continuous two-month period during which the permit is displayed on the land (Article R*600-2 of the Planning Code). For acts taken from 1 July 2026, the administrative courts of appeal rule at first and last instance on disputes, other than compensation claims, concerning the acts on which photovoltaic installations of at least five megawatts and their connection works depend (Article R311-5 of the Code of Administrative Justice); acts taken before that date remain subject to the earlier rules, even if the challenge is brought later (Article 8 of Decree No. 2026-302 of 21 April 2026). For a smaller installation, the administrative court remains in principle competent. A neighbour who challenges must show that the project directly affects the conditions of occupation, use or enjoyment of their property (Article L600-1-2 of the Planning Code). Where the other grounds are unfounded and a defect appears to be capable of regularisation, the court stays its ruling, after inviting the parties to submit observations, and sets a time limit for regularisation, without prejudice to a partial annulment (Article L600-5-1). Both the project developer and the third party therefore have an interest in checking from the outset the capacity of the project, the competent court and the grounds that can genuinely lead to annulment.

Long-term emphyteutic lease and solar panels: who sues in case of defects?

Solar projects often rest on a long-term emphyteutic lease (bail emphytéotique) granted by the owner of the land or building. This lease, for a term of more than eighteen years, gives the tenant a real right and responsibility for improving the property. The Court of Cassation holds that, unless otherwise stipulated, "an emphyteutic lease carries with it, by itself, from the start of enjoyment by effect of the lease and throughout its term, the transfer from the lessor to the tenant of the actions under the ten-year liability guarantee and for compensation for defects affecting the works let" (Cass. 3e civ., 11 July 2024, No. 23-12.491) (our translation). In that case, the lease covered the footprint of photovoltaic panels, their accessories and the space above them; the tenant therefore had standing to sue the insurer under the ten-year guarantee. The outcome turns on the wording of the lease: a clause may reserve certain actions to the lessor. The owner who hosts an installation and the developer who operates it have an interest in setting out clearly the allocation of actions, insurance and maintenance. The firm checks these clauses, together with the conditions precedent linked to the permit and the connection, before the promise or the lease is signed.

Sources and related pages

Official texts and related pages

The sources for this page and the firm's related areas of practice.

Further reading

Page updated on 1 November 2026.

A blocked solar project? Take stock today.

Send the decision received, the application filed and the connection proposal: the firm identifies the blocking stage, the time limit still open and the appropriate legal route.

The latest news.

What our clients say

4,9289 Google reviews
kader ladjouzi
1 month ago

Best real estate law and business law lawyer in Paris. A humane and attentive lawyer, with a wonderful team. Thank you, Maître KOHEN

Translated from French

Janou SAMUEL
2 months ago

Thank you to Maître KOHEN for his analyses of recent case law on fraudulent non-disclosure in property sales. It reassures me about an action for annulment that I am considering after buying a house affected by serious defects intentionally concealed by the seller and not reported by the estate agent; also defects (rising damp) characterised by spreading through-cracks and damp stains, not reported by the estate agent… Worse, defects concealed by the latter or at his instigation, under a coat of paint and by polystyrene tiles glued to the ceiling of a bedroom. And the said estate agent drafted the preliminary contract, which of course contains no information about any of these defects. Just to add that, being 77 years old and suffering from cognitive impairment, I am certain that the estate agent thought I would not be able to discover the deception and above all to establish the fraudulent intent, still less to bring legal proceedings given the complexity and length of the procedure... That is why I am opting for the criminal route, insofar as the intentional concealment of the defects by the seller and then by the estate agent amounts to the fraudulent manoeuvres of art. 313-1 of

Translated from French

Paul MALIK (powlo)
5 months ago

Maître Reda KOHEN assisted me in a dispute concerning a sale agreement with a defaulting party. He provided professional and responsive support, and I highly recommend him.

Translated from French

Rayan Kallout
6 months ago

I highly recommend Maître Reda Kohen. Thanks to his explanations, I was able to recover my security deposit in a situation that seemed blocked. He was responsive, clear, and very professional. A big thank you for his invaluable help!

Translated from French

Naji Jouahri
6 months ago

Excellent support from Maître Kohen in a case combining business law and real estate law. Clear legal analysis from the first meeting, right through to the hearing. Professional and accessible lawyer, I highly recommend his firm in Paris 17.

Translated from French

Halim Tunde
6 months ago

Maître Kohen assisted me in recovering unpaid debts from a defaulting tenant. Procedure mastered from start to finish, from the payment order to eviction. Human, attentive, and always reachable. Thank you for your work.

Translated from French

Cha
6 months ago

As a young student living in an apartment, my landlord tried to make me leave my accommodation even though he had sent me no termination notice. I therefore contacted Mr. Reda Kohen to help me as I couldn’t handle the situation alone. In just 3 days everything was resolved, Maître Kohen defended me and accompanied me with an irreproachable level of commitment and efficiency. I can only recommend his professionalism!

Translated from French

Asmaa Maazaz
7 months ago

I turned to Maître Kohen for a complex real estate dispute and I highly recommend his firm. He is very professional; he thoroughly analyzed my case from the very first appointment and clearly explained the possible options. Thanks to his expertise, we achieved a very favorable outcome. Responsive, a good teacher, and committed, he is a lawyer you can truly trust. Yours faithfully, Miss Maazaz

Translated from French

Contact Mobile
6 days ago

Very satisfied! I would like to thank Maître Esther Cornu here, who managed to resolve a very complicated dispute in a divorce and family law matter...Thanks to Maître Cornu, a judgment was handed down in my favour even though it was far from a foregone conclusion...So I recommend this law firm

Translated from French

Claude Frasson
1 week ago

A precise and concrete analysis and an immediate response. Excellent.

Translated from French

Basel Alali
1 week ago

I highly recommend this lawyer for his professionalism, honesty, and transparency. He helped me successfully and guided me through the process with great care and expertise. What I particularly appreciated was his honest approach and the fact that he recommended practical, cost-effective options instead of immediately pushing for the most expensive solution. He genuinely focused on finding the right approach for my situation. I’m very grateful for his support and would definitely recommend him to anyone looking for a trustworthy and professional lawyer in France.

beatrice lefevre
1 week ago

Thank you for this detailed, precise help, with a proposal at the end on whether or not to continue (very quick response as well)

Translated from French

Jean-pierre Steinmetz
2 weeks ago

Very good advice given by Maître Cornu during our meeting on 16 October.

Translated from French

John Roberts
2 weeks ago

Very professional and responsive service. The lawyer quickly and carefully checked the validity of my wife’s residence permit in light of a specific legal regime. His work gave us clarity, whereas the usual administrative procedures were long and ambiguous. I appreciated his efficiency and professionalism, and I recommend his services.

Translated from French

Jean-François PAPA
3 weeks ago

I would like to warmly thank Maître Esther Cornu for her professionalism, her availability and the quality of her support. In a case of particular importance for my professional future, she showed great responsiveness, rigour and a gift for explaining things, taking the time to answer my questions precisely and to explain the various legal steps to me. I particularly appreciate the clarity of her analyses, her seriousness and her commitment in following up my case. Many thanks to Maître Esther Cornu for listening and for her support. I highly recommend!

Translated from French

Hamid Agouz
3 weeks ago

I was pleasantly surprised by the responsiveness of Mr Reda Cohen, who took the time to answer my questions about my case instantly. It has become so rare these days to find a lawyer who is so available, responsive and attentive, even when it is simply a matter of answering questions. His answers are clear, precise and reassuring. You can tell that he takes the time to understand the situation and to provide relevant answers. Beyond his excellent ratings on Google, it is above all this availability and this seriousness that make the difference. Many thanks to Mr Reda Cohen for his professionalism and his responsiveness. I highly recommend!

Translated from French

Sandra Imbert
3 weeks ago

A huge thank you to Maître Esther Cornu from Kohen Avocats for her support during a particularly difficult time. Her attentiveness, empathy, and humanity touched me deeply. She was able to answer my questions with clarity and sensitivity, while demonstrating great professionalism and fully respecting the confidentiality of the case. Beyond her professional qualities, I met a deeply humane lawyer whose support made a real difference. I sincerely recommend her.

Translated from French

Мария Двирник
1 week ago
Moula Brahimi
1 week ago

Good experience. And good work, thank you for everything.

Translated from French

Faiza Traduction
1 week ago
Alain Arsaut
2 weeks ago

Saw Hassan on the TV news

Translated from French

Beaudrique Abao
2 weeks ago
Krep Events Traiteur Breton
3 weeks ago

very clear article

Translated from French

TOULEIMAT HACHEM
3 weeks ago