Acceptance of works — project owners and contractors
Works acceptance lawyer in Paris: snags, warranties and liability.
Acceptance is the central act of a construction project: it releases the balance of the price, starts the three statutory warranties and extinguishes apparent defects that were not noted. As a works acceptance lawyer in Paris, the firm prepares the acceptance, drafts the snag list and defends you when acceptance is disputed.
Acceptance signed without snags noted extinguishes apparent defects: the preparatory inspection and the snag sheet are completed before the minutes are signed, never afterwards.
Acceptance of works · Paris
Get a first analysis
Project owner, contractor or architect: send the contract, the schedule and the photographs so that the minutes can be prepared — or or to challenge the one already signed. Reply within 24 to 48 hours.
24 à 48 h
first legal
review
Kohen Avocats, Paris 17
Acceptance: what really decides the next ten years
Real estate law · Paris 17th arrondissement
What a works acceptance lawyer in Paris does
- Paris Bar
- Real estate law
- Firm in Paris 17th arrondissement
Lawyer at the Paris Bar — acceptance, snags and construction warranties.
Acceptance is pronounced in the presence of both parties, at the request of the more diligent party, either by agreement or by the court as provided by Article 1792-6 of the French Civil Code (Code civil). It is express when recorded in minutes, but it may also be tacit: taking possession and paying for the works give rise to a presumption of an unequivocal intention to accept. A refusal to accept must be objective and proportionate — unfinished works, major defects, compromised safety — failing which the court may order acceptance and award damages. Apparent defects that were not noted are extinguished, unless they are characterised as latent or as ten-year defects.
Send what you have, even if incomplete: the firm will prioritise and complete the file with you. In an emergency, call +33 6 46 60 58 22.
Official profile in the directory of French lawyers (CNB)Firm at 11 rue Margueritte, 75017 Paris
Four cascading effects
Completion of the works contract, release of the balance, starting point of the statutory warranties, extinction of apparent defects not noted: the date of acceptance governs everything (Article 1792-6 of the Civil Code).
Snags that must be properly drafted
Precise, descriptive, located: a vague snag loses its force. Snags trigger the one-year completion warranty and are the basis for having a defaulting contractor's work completed at its cost and risk.
Tacit acceptance, a double-edged sword
Taking possession and paying give rise to a presumption of an intention to accept — but payment where defects are known and disputed does not amount to tacit acceptance.
The effects
The act from which everything flows
Four rules structure the acceptance of works.
- Acceptance is the act by which the project owner declares that it accepts the work, with or without snags, pronounced in the presence of both parties (Article 1792-6 of the Civil Code).
- Tacit acceptance is presumed from taking possession and paying for the works (Cass. 3e civ., 18 April 2019, No. 18-13.734); full payment of a work package together with taking possession gives rise to a presumption (Cass. 3e civ., 30 January 2019, No. 18-10.197).
- The presumption falls away where the intention to accept is equivocal: payment where defects are known and disputed does not amount to tacit acceptance (Cass. 3e civ., 17 June 1998, No. 96-13.048).
- Acceptance without snags extinguishes apparent defects: a visible defect that was not noted can no longer be relied on, save in cases of fraud or where the defect is characterised as latent — the assessment is made by reference to a normally diligent project owner.
Refusal of acceptance is justified by unfinished works, major defects or compromised safety; it must be objective, reasoned and proportionate, otherwise the contractor obtains judicial acceptance and damages. The date of acceptance — express or tacit — sets the starting point of the one-year completion warranty, the two-year warranty and the ten-year liability: it must be documented with care.
Your documents
What to gather depending on your position
The date and content of the minutes carry ten years of warranties.
Position A
Project owner
- Signed contract, accepted quotes, detailed schedule
- Site meeting reports and photographs before acceptance
- Letters noting snags and insurance certificates
- Acceptance minutes and handwritten annexes
Position B
Contractor
- Contract, quotes and variations, invoices issued
- Schedules met and letters from the project owner
- Formal request for acceptance sent
- Attendance records for the site
Common mistakes: undated photographs and letters; acceptance signed without snags despite visible defects; minutes and handwritten snags not kept.
The firm also handles:
- Judicial acceptance
- Clearing of snags
- Completion at the contractor's cost and risk
- One-year completion warranty
The method
How the firm supports you
The quality of the acceptance decides the outcome of the case for the following ten years.
Step 1
First discussion and sending of documents
Contract, schedule, letters, site photographs: first legal review within 24 to 48 hours.
Step 2
Preparing the acceptance
Check of compliance with the schedule, technical points of attention, acceptance sheet listing the snags to be raised.
Step 3
Assistance at the acceptance meeting
Attendance or advice during the joint inspection, drafting of precise snags, signature or reasoned refusal depending on the condition of the work.
Step 4
After acceptance
Follow-up of the clearing of snags, formal notices, completion at the defaulting contractor's cost and risk, warranty litigation.
On the challenging side: characterising tacit acceptance and its exact date — the issue is often the limitation period for the action.
The timetable
The timeline of a well-run acceptance
From notification of completion to the clearing of snags.
End of works
Day 0. The contractor notifies completion and proposes an acceptance date, ideally by registered letter.
Preparatory inspection
Day 5 to Day 10. Inspection with the architect or a private expert, chronological photographs of each room.
Joint inspection
Day 15. Meeting on site, room-by-room examination, drafting of precise snags in the minutes.
Signature or refusal
Signature with or without snags, or an objective, reasoned refusal if the work is not in a condition to be accepted.
Acceptance + 1 year
One-year completion warranty covering the snags and the defects notified within the year; formal notice, then completion at the contractor's cost and risk.
Acceptance + 2 and + 10 years
Two-year warranty on separable equipment, ten-year liability for serious defects.
The checks
What the firm checks before acting
No action before these points have been checked.
- Existence and date of acceptance: express minutes or tacit acceptance by possession and payment.
- Content of the snags: precision, location, enforceability against the contractor.
- Whether the defects were apparent or latent on the day of acceptance.
- Timetable for clearing the snags and formal notices served.
- Justification for a refusal of acceptance: objective, reasoned, proportionate.
- Warranty periods still to run from the date adopted.
Summary
Situation, evidence, time limit, action
The most frequent configurations at the firm, to quickly calibrate the priority and the procedural weapon.
Situation
Imminent acceptance with apparent defects
Decisive evidence: Dated photographs, contract, site meeting reports.
Time limit: Before the minutes are signed.
Useful action: List the precise snags, with the possible assistance of a private expert.
Situation
Acceptance signed without snags, apparent defects discovered afterwards
Decisive evidence: Chronological photographs, remedial quotes, meeting reports.
Time limit: As early as possible, before the one-year limitation period expires.
Useful action: Look for a latent or ten-year characterisation; otherwise the act extinguishes the defects.
Situation
No minutes, taking possession and payment
Decisive evidence: Proof of payment, letters, taking of possession.
Time limit: Calculated from the last event.
Useful action: Establishing tacit acceptance, calculating the ten-year period.
Situation
Refusal of acceptance disputed by the contractor
Decisive evidence: Contract, schedule, photographs of the condition of the work.
Time limit: As soon as possible.
Useful action: Judicial acceptance before the judicial court (tribunal judiciaire).
Situation
Snags not cleared after one year
Decisive evidence: Acceptance minutes, formal notices, letters.
Time limit: During the one-year completion warranty.
Useful action: Works carried out at the cost and risk of the defaulting contractor.
Situation
Defect discovered 9 years after acceptance
Decisive evidence: Photographs, quotes, technical certificate, date of acceptance.
Time limit: Before the ten-year period expires.
Useful action: Urgent application for an expert assessment under Article 145 of the French Code of Civil Procedure (Code de procédure civile), action under the ten-year builder's liability.
Practical cases from the firm
Anonymised examples. The figures correspond to real cases, rounded for the sake of discretion.
The anonymised examples below illustrate the variety of situations handled. The figures correspond to real cases but have been rounded for the sake of discretion.
Tacit acceptance upheld, project owner's claim dismissed
Renovation of a Paris flat without acceptance minutes. Contract of €75,000 paid in full, possession actually taken. The court finds tacit acceptance from taking possession and full payment of the balance, and sets the date at the last event. The project owner brought proceedings 11 years later; the action was declared time-barred.
Action: characterisation of tacit acceptance. Outcome: contractor cleared of ten-year liability.
Precise snags, release of €12,200 retention
Acceptance of a major renovation with 23 precise snags listed in the minutes: badly laid tiles, long cracks, electrical defects, unpointed skirting boards. After formal notice, the contractor refuses to carry out the remedial work. Works carried out at the contractor's cost and risk by a second contractor. Release of a €12,200 retention obtained.
Action: Article 1792-6, paragraph 4 of the Civil Code. Outcome: remedial work done and retention released.
Refusal of acceptance justified by 8 major defects
New house delivered with 8 documented major defects: failing waterproofing, windows not compliant with the DTU (technical standards), uninsulated floor, poorly partitioned rooms. The project owner refuses acceptance. The contractor applies to the court for judicial acceptance. The judge records the condition of the work and confirms the refusal; a second set of minutes follows once the defects are remedied.
Action: judicial acceptance unfavourable to the contractor. Outcome: full remedial work before a new acceptance.
Frequently asked questions
Your questions: acceptance of works
What is acceptance of works?
Acceptance is the act by which the project owner declares that it accepts the work, with or without snags. Article 1792-6 of the Civil Code provides that it takes place at the request of the more diligent party, either by agreement or, failing that, by the court
and that it is in any event, pronounced in the presence of both parties
(our translation).
In practice, it takes the form of minutes signed by the project owner and the contractor, which may list snags or be signed without any. Acceptance may also be tacit, where the project owner's conduct shows an unequivocal intention to accept the work. It is the central act of construction law: it triggers the statutory warranties and starts the time limits running.
What are the legal effects of acceptance?
Acceptance has four main effects. First, it marks the completion of the works contract and releases the balance of the works price. Second, it is the starting point of the three statutory warranties: completion (one year), proper functioning (two years) and ten-year liability (ten years). Third, it extinguishes apparent defects that were not noted, which can no longer be invoked under the builders' liability regime save in the particular case of fraud or fraudulent misrepresentation (dol).
Fourth, it transfers custody of the work from the builder to the project owner, which is decisive for insurance. The date of acceptance is both a starting point and an end point: before it, the builder is bound by an obligation to achieve a result as to completion and conformity; after it, liability arises only under the conditions and within the periods of the statutory warranties.
How should snags be worded?
Snags must be listed in the acceptance minutes, precisely and descriptively. They identify the location, the nature of the defect observed and, where appropriate, the remedial work expected. A snag worded in general terms (finishing work to be redone
) will be harder to enforce than a detailed one (long cracks in the north-east corner of the living room, badly pointed skirting boards on the south wall, two cracked tiles in the bathroom
).
Precision determines scope. The one-year completion warranty covers the defects flagged by snags in the minutes or by later written notification. The project owner may also annex a photographic file to the minutes, sign an addendum detailing the remedial work and set a deadline for its completion. Signing an acceptance without snags amounts to a waiver of the right to rely on defects that were apparent on the day of acceptance, other than ten-year and proper-functioning defects.
What is tacit acceptance?
Tacit acceptance is acceptance resulting from unequivocal conduct by the project owner showing an intention to accept the work, without any minutes having been signed. The Third Civil Chamber of the Court of Cassation has set the test: taking possession of the work and paying for it give rise to a presumption of the project owner's unequivocal intention to accept it, with or without snags (Cass. 3e civ., 18 April 2019, No. 18-13.734, published in the Bulletin).
The Court has also held that completion of the whole of the work is not a condition for taking possession of a package and for its acceptance
and that payment of the entire price of the works of a package and its taking of possession by the project owner give rise to a presumption of tacit acceptance
(our translation) (Cass. 3e civ., 30 January 2019, No. 18-10.197, published in the Bulletin). The presumption is rebuttable: it can be overturned by proof of a contrary intention, for example if the project owner has consistently disputed the quality of the works and made express reservations.
Can the project owner refuse acceptance?
Yes, where the work is not in a condition to be accepted. The project owner may refuse acceptance if the works are unfinished, if major defects make the work unfit for its intended purpose, or if the safety of the occupants is compromised. The refusal must be objective, reasoned and proportionate to the defects observed. An abusive refusal, that is, one based on minor or non-existent defects, exposes the project owner to a claim for judicial acceptance and to damages.
In practice, if the refusal persists, the builder may apply to the court for judicial acceptance. The judge then pronounces acceptance, possibly with snags, by reference to the technical condition of the work and the conclusions of an expert. For the project owner, the most prudent course with a partly defective work is often acceptance with precise snags rather than an outright refusal.
How long is there to clear the snags?
Article 1792-6 of the Civil Code does not set a single mandatory time limit. The text provides that the time needed to carry out the remedial work is fixed by mutual agreement between the project owner and the contractor concerned
(our translation). In practice, contracts generally provide for a period for clearing snags within the weeks or months following acceptance, sometimes 30 to 90 days depending on the nature of the works.
The issue lies in the sanction. The text continues: failing such agreement or if the work is not carried out within the set period, the work may, after a formal notice that has remained unsuccessful, be carried out at the cost and risk of the defaulting contractor
(our translation). The one-year completion warranty runs for one year from acceptance and requires the contractor to remedy the defects noted as snags or notified in writing within that year. Actual clearing must be recorded by agreement or, failing that, by the court.
Does full payment amount to acceptance?
Full payment of the works does not, on its own, amount to acceptance. But combined with taking possession, it gives rise to a presumption of the project owner's unequivocal intention to accept the work. The Third Civil Chamber held on 18 April 2019 that taking possession of the work and paying for the works give rise to a presumption of that intention. This statutory presumption requires the judge to apply it, absent proof to the contrary.
Where taking possession and payment are spread over time, the date adopted for tacit acceptance is that of the last, latest event. The Third Civil Chamber confirmed this rule on 12 November 2020 in a case where possession was taken in September 2005 and full payment was made on 26 May 2006: the date of tacit acceptance was set at 26 May 2006.
Does taking possession amount to acceptance?
Taking possession alone is generally not enough to establish acceptance. A body of evidence showing the project owner's unequivocal intention is required: taking possession, payment, absence of express snags, possibly upkeep of the premises or use in line with the intended purpose. In an older decision, the Third Civil Chamber held that taking possession accompanied by the most express reservations about known defects does not amount to tacit acceptance (Cass. 3e civ., 17 June 1998, No. 96-13.048).
The presumption established by case law since 2019, however, reverses the burden of proof: where taking possession is combined with full payment, a project owner who disputes acceptance must prove a contrary intention (for example through regular letters of protest, bailiff's reports on the defects, or referral to a private expert). To avoid the debate, it is better to sign precise minutes, whether with or without snags.
Which defects should be flagged at acceptance?
All apparent defects must be flagged in the minutes in the form of snags. Acceptance without snags extinguishes the defects that were apparent on the day of acceptance: they can no longer be invoked under the builder's contractual liability, save in the particular case of fraudulent misrepresentation (dol). Typically concerned are visible cracks, finishing defects, deviations from the plans or the specifications of the contract, and aesthetic imperfections.
Whether a defect is apparent or latent is assessed by reference to a normally diligent project owner, at the precise time of acceptance. Damage is apparent if not only its visible manifestation but also its causes and consequences were foreseeable. Latent defects, or those not yet revealed at acceptance, remain covered by the ten-year liability or the proper-functioning warranty depending on their nature. For more on classification, see our page on construction defects.
Does the architect sign the minutes?
Yes, where the architect has been given a site supervision brief. The architect, as project manager for the execution of the works, assists the project owner at the acceptance meeting, advises on the snags to be raised and signs the minutes in an assisting capacity. The signature engages the architect's professional duty of advice: an architect who fails to flag an apparent defect at the time of acceptance may be held liable jointly and severally (in solidum) with the contractor.
The architect's absence from the acceptance meeting is itself a problem. A project owner who pronounces acceptance without the project manager risks missing technical defects that only a professional can identify. If the assistance brief is provided for in the contract, an architect absent without legitimate reason may incur liability. The presence of all the parties at the minutes is a good practice that proves decisive in later litigation.
What if the contractor does not remedy the snags?
Article 1792-6 of the Civil Code lays down the procedure: failing such agreement or if the work is not carried out within the set period, the work may, after a formal notice that has remained unsuccessful, be carried out at the cost and risk of the defaulting contractor
(our translation). The project owner must therefore first serve a written formal notice, by registered letter with acknowledgement of receipt, setting a reasonable period for the remedial work.
If the formal notice has no effect, the project owner may have the work carried out by another contractor, at the cost and risk of the defaulting contractor. Prudence calls for having the non-performance recorded by a bailiff before the second contractor steps in, and for keeping quotes, invoices and photographs from before and after the remedial work. The project owner may then apply to the court for reimbursement of the sums incurred, in addition, where applicable, to compensation for loss of enjoyment and costs. Retention money, if provided for, may be drawn on.
Does the one-year completion warranty run after snags are noted?
Yes. The one-year completion warranty runs for one year from acceptance and, under Article 1792-6 of the Civil Code, covers the defects flagged by means of snags noted in the acceptance minutes, or by written notification for those revealed after acceptance
(our translation). The warranty rests on the contractor who carried out the works concerned.
This warranty is distinct from the ten-year liability. It covers all defects, even minor ones, flagged during the year following acceptance. Ten-year liability covers only defects that compromise the solidity of the work or make it unfit for its intended purpose. The two warranties can overlap: the same defect, flagged within the year, may fall under both the completion warranty and ten-year liability if it is serious enough. The clearing of snags must be recorded, by agreement or by the court.
What is the time limit for ten-year defects?
Article 1792-4-1 of the Civil Code provides that any person whose liability may be engaged under Articles 1792 to 1792-4 is discharged from the liabilities and warranties weighing on them, under Articles 1792 to 1792-2, after ten years from acceptance of the works
(our translation). The starting point is the date of acceptance, express or tacit.
The stakes are decisive. A defect revealed 9 years and 11 months after acceptance remains covered by ten-year liability; a defect revealed 10 years and one month after acceptance is time-barred. The project owner must anticipate the limitation period: notify the claim to the building-damage insurer where applicable, have the defects recorded by a bailiff, and serve an urgent application for an expert assessment under Article 145 of the Code of Civil Procedure to interrupt the period. To go further, see our page on ten-year builder's liability.
Can an expert attend the acceptance?
Yes, and it is even recommended for complex sites or high-stakes operations. The project owner may appoint a private technical expert (architect, engineering consultancy, expert registered with a court of appeal) to assist at the acceptance meeting. The expert draws up a detailed report, identifies the apparent defects, proposes precise snags and measures their technical impact.
Their presence, separate from that of the architect who supervised the site, provides an independent analysis that can be relied on against the other parties. In later litigation, the report and the recommendation sheet on the snags to be raised may be put before the court and support the characterisation of the defects. The cost of a private expert, generally between €800 and €2,500 for a home acceptance, is a preventive investment that avoids disputes that are often more costly. To go further, see our page on building expert assessment.
Which court has jurisdiction in Paris?
The Paris judicial court has jurisdiction over acceptance disputes where the building is located in Paris. The rule of territorial jurisdiction rests, in real property matters, on the location of the building. For an urgent application for an expert assessment, where the measure concerns a building, Article 145 of the Code of Civil Procedure requires the court of the place where the building is located.
For sites in the inner suburbs, the judicial court of Bobigny, Créteil, Nanterre or Versailles may have jurisdiction depending on the municipality. The firm, based at 11 rue Margueritte 75017 Paris, regularly pleads before all of these courts and coordinates court-appointed expert assessments throughout the jurisdiction of the Paris court of appeal. For sensitive operations, anticipating territorial jurisdiction from the contract stage makes it possible to arrange, where appropriate, a valid jurisdiction clause between traders.
Sources and related pages
Official texts and related pages
The sources for this page and the firm's related areas of practice.
Further reading
Page updated on 11 June 2026.
Acceptance to secure? Act today.
Project owner, contractor or architect: send the contract, the schedule and the photographs so that the minutes can be prepared — or or to challenge the one already signed. Reply within 24 to 48 hours.
The latest news.
What our clients say
Best real estate law and business law lawyer in Paris. A humane and attentive lawyer, with a wonderful team. Thank you, Maître KOHEN
Translated from French
Thank you to Maître KOHEN for his analyses of recent case law on fraudulent non-disclosure in property sales. It reassures me about an action for annulment that I am considering after buying a house affected by serious defects intentionally concealed by the seller and not reported by the estate agent; also defects (rising damp) characterised by spreading through-cracks and damp stains, not reported by the estate agent… Worse, defects concealed by the latter or at his instigation, under a coat of paint and by polystyrene tiles glued to the ceiling of a bedroom. And the said estate agent drafted the preliminary contract, which of course contains no information about any of these defects. Just to add that, being 77 years old and suffering from cognitive impairment, I am certain that the estate agent thought I would not be able to discover the deception and above all to establish the fraudulent intent, still less to bring legal proceedings given the complexity and length of the procedure... That is why I am opting for the criminal route, insofar as the intentional concealment of the defects by the seller and then by the estate agent amounts to the fraudulent manoeuvres of art. 313-1 of
Translated from French
Maître Reda KOHEN assisted me in a dispute concerning a sale agreement with a defaulting party. He provided professional and responsive support, and I highly recommend him.
Translated from French
I highly recommend Maître Reda Kohen. Thanks to his explanations, I was able to recover my security deposit in a situation that seemed blocked. He was responsive, clear, and very professional. A big thank you for his invaluable help!
Translated from French
Excellent support from Maître Kohen in a case combining business law and real estate law. Clear legal analysis from the first meeting, right through to the hearing. Professional and accessible lawyer, I highly recommend his firm in Paris 17.
Translated from French
Maître Kohen assisted me in recovering unpaid debts from a defaulting tenant. Procedure mastered from start to finish, from the payment order to eviction. Human, attentive, and always reachable. Thank you for your work.
Translated from French
As a young student living in an apartment, my landlord tried to make me leave my accommodation even though he had sent me no termination notice. I therefore contacted Mr. Reda Kohen to help me as I couldn’t handle the situation alone. In just 3 days everything was resolved, Maître Kohen defended me and accompanied me with an irreproachable level of commitment and efficiency. I can only recommend his professionalism!
Translated from French
I turned to Maître Kohen for a complex real estate dispute and I highly recommend his firm. He is very professional; he thoroughly analyzed my case from the very first appointment and clearly explained the possible options. Thanks to his expertise, we achieved a very favorable outcome. Responsive, a good teacher, and committed, he is a lawyer you can truly trust. Yours faithfully, Miss Maazaz
Translated from French
Very satisfied! I would like to thank Maître Esther Cornu here, who managed to resolve a very complicated dispute in a divorce and family law matter...Thanks to Maître Cornu, a judgment was handed down in my favour even though it was far from a foregone conclusion...So I recommend this law firm
Translated from French
A precise and concrete analysis and an immediate response. Excellent.
Translated from French
I highly recommend this lawyer for his professionalism, honesty, and transparency. He helped me successfully and guided me through the process with great care and expertise. What I particularly appreciated was his honest approach and the fact that he recommended practical, cost-effective options instead of immediately pushing for the most expensive solution. He genuinely focused on finding the right approach for my situation. I’m very grateful for his support and would definitely recommend him to anyone looking for a trustworthy and professional lawyer in France.
Thank you for this detailed, precise help, with a proposal at the end on whether or not to continue (very quick response as well)
Translated from French
Very good advice given by Maître Cornu during our meeting on 16 October.
Translated from French
Very professional and responsive service. The lawyer quickly and carefully checked the validity of my wife’s residence permit in light of a specific legal regime. His work gave us clarity, whereas the usual administrative procedures were long and ambiguous. I appreciated his efficiency and professionalism, and I recommend his services.
Translated from French
I would like to warmly thank Maître Esther Cornu for her professionalism, her availability and the quality of her support. In a case of particular importance for my professional future, she showed great responsiveness, rigour and a gift for explaining things, taking the time to answer my questions precisely and to explain the various legal steps to me. I particularly appreciate the clarity of her analyses, her seriousness and her commitment in following up my case. Many thanks to Maître Esther Cornu for listening and for her support. I highly recommend!
Translated from French
I was pleasantly surprised by the responsiveness of Mr Reda Cohen, who took the time to answer my questions about my case instantly. It has become so rare these days to find a lawyer who is so available, responsive and attentive, even when it is simply a matter of answering questions. His answers are clear, precise and reassuring. You can tell that he takes the time to understand the situation and to provide relevant answers. Beyond his excellent ratings on Google, it is above all this availability and this seriousness that make the difference. Many thanks to Mr Reda Cohen for his professionalism and his responsiveness. I highly recommend!
Translated from French
A huge thank you to Maître Esther Cornu from Kohen Avocats for her support during a particularly difficult time. Her attentiveness, empathy, and humanity touched me deeply. She was able to answer my questions with clarity and sensitivity, while demonstrating great professionalism and fully respecting the confidentiality of the case. Beyond her professional qualities, I met a deeply humane lawyer whose support made a real difference. I sincerely recommend her.
Translated from French
Good experience. And good work, thank you for everything.
Translated from French
Saw Hassan on the TV news
Translated from French
very clear article
Translated from French
Loading…
Your cookies
We use cookies to measure the effectiveness of our campaigns and improve the site. You can change your choice at any time.