VEFA — off-plan buyers
Off-plan purchase lawyer Paris: delays, snags and stage payments.
Buying off plan transfers ownership as the building progresses: everything turns on the reservation contract, the delivery date and the delivery report. As an off-plan purchase lawyer in Paris, the firm reviews the documents before signature and pursues compensation for the developer's delays.
A delivery has to be prepared: snags are recorded in the delivery report, precisely and with dates, and the 5% retention is put in place before the keys are handed over, not after.
VEFA · Paris
Get a first analysis
Contract to review, delay to claim compensation for or delivery to prepare: send the reservation contract, the deed and the developer's letters. The firm replies within 24 to 48 business hours.
24 à 48 h
first legal
review
Kohen Avocats, Paris 17
Off-plan sale: what really decides the case
Real estate law · Paris 17th arrondissement
What an off-plan purchase lawyer in Paris does
- Paris Bar
- Real estate law
- Firm in Paris 17th arrondissement
Lawyer at the Paris Bar — off-plan sales and disputes with developers.
The off-plan sale (VEFA), governed by Articles 1601-1 and 1601-3 of the French Civil Code (Code civil) and Articles L. 261-1 et seq. of the Construction and Housing Code (CCH), transfers ownership of the land at the deed and then of the buildings as the works progress. A non-professional buyer may withdraw within ten days (L. 271-1). Unjustified late delivery makes the developer liable (Articles 1103 and 1217): contractual penalties or proven compensation. At delivery: a joint delivery report, precise snags, 5% retention until they are cleared, then the statutory warranties — one-year completion, two-year equipment and ten-year.
Send what you have, even if incomplete: the firm will prioritise and complete the file with you. In an emergency, call +33 6 46 60 58 22.
Official profile in the directory of French lawyers (CNB)Firm at 11 rue Margueritte, 75017 Paris
A tightly regulated contract
Detailed description, price and terms, delivery period, financial completion guarantee: the particulars required by Article L. 261-11 of the Construction and Housing Code (CCH) determine how sound the contract is, with the descriptive notice and plans having contractual value.
Delay is compensated
Contractual penalties per day of delay, or proof of loss: loss of use, lost rental opportunity, lost tax advantage, non-material loss — recent case law assesses each head of loss separately.
The 5% retention
As long as snags have not been cleared, the buyer withholds 5% of the price (Article R. 261-14), held by the notary or an escrow agent. Completion itself is reviewed by the courts.
The framework
From the reservation contract to handing over the keys
Four rules structure off-plan sale disputes.
- Transfer of ownership is immediate and progressive: the land at signature of the notarial deed, the buildings as the works progress (Articles 1601-1 and 1601-3 of the Civil Code).
- The contract contains the particulars required by Article L. 261-11 of the CCH — description, price, delivery period, financial completion guarantee — and the non-professional buyer may withdraw within ten days (Article L. 271-1).
- Unjustified delay engages the developer's contractual liability (Articles 1103 and 1217): the seller must prove completion by the agreed date (CA Versailles, 30 June 2025, No. RG 23/01404).
- Clauses suspending the delivery period are applied strictly: a proven legitimate event, a certificate from the project manager, notification — failing which the delay remains attributable to the developer.
Compensation is assessed head by head: loss of use, lost chance to let or sell, lost tax advantage, non-material loss — lost chances are never compensated at the same level as the gain missed (TJ Bobigny, 9 February 2026, No. RG 25/03747).
Your documents
What to send depending on your situation
The reservation contract and the delivery report carry most of the dispute.
Position A
Before signature
- Reservation contract and draft notarial deed
- Descriptive notice and attached plans
- Financial completion guarantee and identity of the guarantor
- Schedule of stage payments and clauses suspending the delivery period
Position B
Delay or delivery
- Notarial deed and contractual delivery date
- Developer's letters and notices of suspension
- Delivery report and snags recorded
- Evidence of loss: expected rent, tax scheme, costs
Common mistakes: signing the delivery report without precise snags; releasing the 5% before the snags have actually been cleared.
The firm also secures:
- Financial completion guarantee
- Non-conformities at delivery
- Irregular stage payment calls
- Statutory warranties after delivery
The method
How the firm supports you
A demanding review of the reservation contract avoids most later disputes.
Step 1
Pre-contract analysis
Developer, financial guarantor, contractual date, suspension clauses, terms of the stage payments: consistency of the file before signature.
Step 2
Monitoring the schedule
Checking the justifications given for delay: legitimate event, project manager's certificate, proper notification.
Step 3
Assisted delivery
Preparing the delivery report, precise and dated snags, 5% retention held by the notary or an escrow agent.
Step 4
Compensation
Formal notice to the developer, head-by-head assessment of losses, writ of summons before the judicial court if the amicable route fails.
After delivery, the statutory warranties take over: one-year completion, two-year equipment and ten-year.
The timetable
The timeline of an off-plan sale
From reservation to the clearing of snags.
Reservation
Reservation contract, deposit, checks on the developer and the completion guarantor.
Notarial deed
Particulars required by Article L. 261-11 checked; the non-professional may withdraw within ten days (L. 271-1).
Stage payments
Building works. Staged payments according to progress, with the regularity of the calls checked.
Contractual date
Failing proven completion, the delay is attributable to the developer: penalties or compensation for loss.
Delivery
Joint delivery report, precise snags, 5% retention (R. 261-14).
After delivery
Snags cleared, release of the 5%, statutory warranties — one-year completion, two-year equipment, ten-year.
The checks
What the firm checks before acting
No signature or writ of summons before these points have been validated.
- Mandatory particulars of the contract: description, price, period, financial completion guarantee.
- Clauses suspending the delivery period and their notification procedure.
- Calculation of the delay: contractual date, justifications produced, project manager's certificate.
- Quantifiable losses: loss of use, lost rental or tax opportunity, non-material loss.
- Delivery report: precision of the snags, 5% retention.
- Completion within the meaning of Article R. 261-1, which the courts can review in case of disagreement.
Frequently asked questions
Your questions: off-plan sales
What is an off-plan sale (VEFA)?
A sale of a building to be constructed is one in which the seller undertakes to build a building within a period set by the contract (Article 1601-1 of the Civil Code). The off-plan sale (VEFA), governed by Article 1601-3 of the Civil Code and Articles L. 261-1 et seq. of the Construction and Housing Code, brings about an immediate transfer of ownership: the buyer becomes owner of the land on signature of the notarial deed, then of the buildings as they are built.
This unusual mechanism calls for particular vigilance from the reservation contract onwards: the developer, the financial guarantor, the contractual delivery date, the clauses suspending the period and the terms of the stage payments should all be analysed before signing.
What particulars must an off-plan sale contract contain?
Article L. 261-11 of the Construction and Housing Code requires several mandatory particulars: a detailed description of the building, the price and payment terms, the delivery period, and a financial completion or refund guarantee. The descriptive notice and the plans annexed to the contract have contractual value.
The absence or imprecision of any of these particulars weakens the contract and may open the way to a partial challenge.
Can you withdraw after signing an off-plan sale?
The non-professional buyer has enhanced protection: Article L. 271-1 of the Construction and Housing Code gives a ten-day withdrawal period after notification of the deed. During that period, the buyer may withdraw freely, without giving reasons and without penalty.
After that, the contract binds the buyer, who must meet the stage payment calls according to the contractual schedule.
What can you do if delivery is late?
The delivery date is an essential element of the contract. Unjustified delay engages the developer's contractual liability under Articles 1103 and 1217 of the Civil Code. The Versailles Court of Appeal has recalled this: where the seller fails to prove completion as contractually required by the agreed date, unjustified late delivery is established (CA Versailles, 1st and 4th chambers, 30 June 2025, No. RG 23/01404).
Where the contract provides for late-delivery penalties, they apply per day of delay, based on a percentage of the sale price. Failing that, the buyer must prove their loss.
How is delay compensated when the contract provides no penalties?
The loss must be proved and assessed head by head. The Versailles Court of Appeal awarded €8,000 for loss of use over sixteen months of delay on a property valued at €480,000, noting that the delay causes loss of use in the broad sense, which may consist of a lost chance to sell earlier (CA Versailles, 30 June 2025, No. RG 23/01404).
The judicial court of Bobigny awarded compensation for a delay of more than 1,228 days: €16,000 for the lost chance of receiving rent, €12,266 for the lost chance of benefiting from the Pinel tax scheme and €3,000 for non-material loss (TJ Bobigny, 9 February 2026, No. RG 25/03747). Lost rent and a lost tax advantage are compensated as lost chances, never at the same level as the gain missed.
Can the developer justify the delay by legitimate causes?
Clauses suspending the delivery period are strictly applied. The developer must prove the legitimate event relied on — bad weather, contractor failure, administrative order — and produce the project manager's certificate provided for in the contract.
Case law accepts the validity of a clause providing for a doubling of the suspension period, but compliance with the notification procedure remains essential: without a certificate and without notification, the delay remains attributable to the developer.
How does delivery work in an off-plan sale?
Delivery takes the form of a report recording completion and taking of possession, signed jointly by the seller and the buyer. This document fixes the date of completion within the meaning of Article R. 261-1 of the Construction and Housing Code and lists the snags noted by the buyer.
Snags must be precise: nature of the defect, location, seriousness, proposed period for remedy. A snag that is too vague or undated loses its evidential force.
Can you withhold part of the price until snags are cleared?
Yes. The 5% retention of the price provided for by Article R. 261-14 of the Construction and Housing Code allows the buyer to withhold that portion until the snags are cleared, generally with the notary or an escrow agent.
Who decides whether the building is complete?
The notion of completion is not left to the seller's sole assessment: it is subject to judicial review. In case of disagreement between the parties, it is for the trial judge, where the completion guarantor has applied for payment of the 95% portion of the price, to assess whether the building is complete within the meaning of Article R. 261-1 (Cass. 3e civ., 26 November 2020, No. 18-17.617).
What warranties apply after delivery with snags?
The buyer keeps the benefit of the statutory warranties: the one-year completion warranty of Article 1792-6 of the Civil Code covers for one year all defects noted at acceptance or appearing within the year; the two-year equipment warranty of Article 1792-3 covers the proper functioning of separable equipment for two years; the ten-year builder's liability of Article 1792 covers for ten years defects affecting structural soundness or making the work unfit for its purpose.
Sources and related pages
Official texts and related pages
The sources for this page and the firm's related areas of practice.
Further reading
Page updated on 11 June 2026.
An off-plan project or dispute? Act today.
Contract to review, delay to claim compensation for or delivery to prepare: send the reservation contract, the deed and the developer's letters. The firm replies within 24 to 48 business hours.
The latest news.
What our clients say
Best real estate law and business law lawyer in Paris. A humane and attentive lawyer, with a wonderful team. Thank you, Maître KOHEN
Translated from French
Thank you to Maître KOHEN for his analyses of recent case law on fraudulent non-disclosure in property sales. It reassures me about an action for annulment that I am considering after buying a house affected by serious defects intentionally concealed by the seller and not reported by the estate agent; also defects (rising damp) characterised by spreading through-cracks and damp stains, not reported by the estate agent… Worse, defects concealed by the latter or at his instigation, under a coat of paint and by polystyrene tiles glued to the ceiling of a bedroom. And the said estate agent drafted the preliminary contract, which of course contains no information about any of these defects. Just to add that, being 77 years old and suffering from cognitive impairment, I am certain that the estate agent thought I would not be able to discover the deception and above all to establish the fraudulent intent, still less to bring legal proceedings given the complexity and length of the procedure... That is why I am opting for the criminal route, insofar as the intentional concealment of the defects by the seller and then by the estate agent amounts to the fraudulent manoeuvres of art. 313-1 of
Translated from French
Maître Reda KOHEN assisted me in a dispute concerning a sale agreement with a defaulting party. He provided professional and responsive support, and I highly recommend him.
Translated from French
I highly recommend Maître Reda Kohen. Thanks to his explanations, I was able to recover my security deposit in a situation that seemed blocked. He was responsive, clear, and very professional. A big thank you for his invaluable help!
Translated from French
Excellent support from Maître Kohen in a case combining business law and real estate law. Clear legal analysis from the first meeting, right through to the hearing. Professional and accessible lawyer, I highly recommend his firm in Paris 17.
Translated from French
Maître Kohen assisted me in recovering unpaid debts from a defaulting tenant. Procedure mastered from start to finish, from the payment order to eviction. Human, attentive, and always reachable. Thank you for your work.
Translated from French
As a young student living in an apartment, my landlord tried to make me leave my accommodation even though he had sent me no termination notice. I therefore contacted Mr. Reda Kohen to help me as I couldn’t handle the situation alone. In just 3 days everything was resolved, Maître Kohen defended me and accompanied me with an irreproachable level of commitment and efficiency. I can only recommend his professionalism!
Translated from French
I turned to Maître Kohen for a complex real estate dispute and I highly recommend his firm. He is very professional; he thoroughly analyzed my case from the very first appointment and clearly explained the possible options. Thanks to his expertise, we achieved a very favorable outcome. Responsive, a good teacher, and committed, he is a lawyer you can truly trust. Yours faithfully, Miss Maazaz
Translated from French
Very satisfied! I would like to thank Maître Esther Cornu here, who managed to resolve a very complicated dispute in a divorce and family law matter...Thanks to Maître Cornu, a judgment was handed down in my favour even though it was far from a foregone conclusion...So I recommend this law firm
Translated from French
A precise and concrete analysis and an immediate response. Excellent.
Translated from French
I highly recommend this lawyer for his professionalism, honesty, and transparency. He helped me successfully and guided me through the process with great care and expertise. What I particularly appreciated was his honest approach and the fact that he recommended practical, cost-effective options instead of immediately pushing for the most expensive solution. He genuinely focused on finding the right approach for my situation. I’m very grateful for his support and would definitely recommend him to anyone looking for a trustworthy and professional lawyer in France.
Thank you for this detailed, precise help, with a proposal at the end on whether or not to continue (very quick response as well)
Translated from French
Very good advice given by Maître Cornu during our meeting on 16 October.
Translated from French
Very professional and responsive service. The lawyer quickly and carefully checked the validity of my wife’s residence permit in light of a specific legal regime. His work gave us clarity, whereas the usual administrative procedures were long and ambiguous. I appreciated his efficiency and professionalism, and I recommend his services.
Translated from French
I would like to warmly thank Maître Esther Cornu for her professionalism, her availability and the quality of her support. In a case of particular importance for my professional future, she showed great responsiveness, rigour and a gift for explaining things, taking the time to answer my questions precisely and to explain the various legal steps to me. I particularly appreciate the clarity of her analyses, her seriousness and her commitment in following up my case. Many thanks to Maître Esther Cornu for listening and for her support. I highly recommend!
Translated from French
I was pleasantly surprised by the responsiveness of Mr Reda Cohen, who took the time to answer my questions about my case instantly. It has become so rare these days to find a lawyer who is so available, responsive and attentive, even when it is simply a matter of answering questions. His answers are clear, precise and reassuring. You can tell that he takes the time to understand the situation and to provide relevant answers. Beyond his excellent ratings on Google, it is above all this availability and this seriousness that make the difference. Many thanks to Mr Reda Cohen for his professionalism and his responsiveness. I highly recommend!
Translated from French
A huge thank you to Maître Esther Cornu from Kohen Avocats for her support during a particularly difficult time. Her attentiveness, empathy, and humanity touched me deeply. She was able to answer my questions with clarity and sensitivity, while demonstrating great professionalism and fully respecting the confidentiality of the case. Beyond her professional qualities, I met a deeply humane lawyer whose support made a real difference. I sincerely recommend her.
Translated from French
Good experience. And good work, thank you for everything.
Translated from French
Saw Hassan on the TV news
Translated from French
very clear article
Translated from French
Loading…
Your cookies
We use cookies to measure the effectiveness of our campaigns and improve the site. You can change your choice at any time.