Building permit challenge — neighbours and permit holders

Building permit challenge lawyer in Paris: act within the time limits.

Two months to challenge from the posting of the notice on site, fifteen clear days to notify the challenge on pain of inadmissibility: planning litigation is a matter of deadlines. The firm, as a building permit challenge lawyer in Paris, acts for neighbours and associations as well as for permit holders defending their permits.

Notice posted more than a month ago? The two-month period and the notification within fifteen days allow no leeway. Send the permit decision and the report of the site notice immediately.

Building permit challenge · Paris

Get a first analysis

Whether you are a neighbour, an association or a permit holder, the two-month period often decides the outcome of the case. Send the permit decision, the report of the site notice and the plans: the firm replies within 24 to 48 hours.

24 à 48 h

first legal
review

€80incl. VAT

Preliminary review of your case. Examination of your documents and a first written analysis by Reda Kohen, within 24 to 48 business hours. Payment is made online after this form is sent.

  • Up to 1 GB of documents, folders and subfolders accepted
  • Secure payment, no banking data stored
  • Terms and fee agreement

Click or drag your files here
All formats accepted (PDF, Word, images, etc.)

Sending...

Payment constitutes a request for immediate performance of your analysis. Your data is used only to process your request. Terms · Privacy policy.

In the media

  • Lexbase

Kohen Avocats, Paris 17

Permit challenges: what really decides the case

Reda Kohen, lawyer at the Paris Bar
Reda KohenLawyer at the Paris Bar

Real estate law · Paris 17th arrondissement

What a building permit challenge lawyer in Paris does

  • Paris Bar
  • Real estate law
  • Firm in Paris 17th

Lawyer at the Paris Bar — real estate law and administrative planning litigation.

A neighbour who challenges a permit must show standing to bring the claim (Article L. 600-1-2), apply to the administrative court (tribunal administratif) within two months of the posting of the notice, and notify the challenge within fifteen clear days on pain of inadmissibility (Article R. 600-1). An urgent application for suspension (référé suspension) can halt the works where there is urgency and a serious doubt; it is governed by Article L. 521-1 of the Code of Administrative Justice. The permit holder, for their part, defends the permit through regularisation: an amending permit (permis modificatif) issued under the court's supervision.

Send what you have, even if incomplete: the firm will prioritise and complete the file with you. In an emergency, call +33 6 46 60 58 22.

Official profile in the directory of French lawyers (CNB)Firm at 11 rue Margueritte, 75017 Paris

Two months, not a day more

The period runs from the first day of a continuous two-month period of regular posting of the notice on the site (Article R. 600-2 of the Planning Code). A non-compliant or interrupted posting reopens the period.

The R. 600-1 notification: a hard cut-off

The challenge must be notified to the author of the decision and to the permit holder by registered letter within fifteen clear days of filing. Without it, the claim is dismissed without examination of the merits, with no possibility of regularisation.

Regularising rather than annulling

The court may stay proceedings to allow an amending permit (Article L. 600-5-1). For the permit holder, regularisation is the lever that saves the project.

The rules

A system of time limits and admissibility rules

Four rules govern building permit litigation.

  1. The time limit for third-party challenges runs from the first day of a continuous two-month period of regular posting of the notice on the site: visible, legible, stating the characteristics of the project and the available means of challenge (Articles R. 600-2 and R. 424-15 of the Planning Code).
  2. Standing requires that the project directly affect the conditions of occupation, use or enjoyment of the property (Article L. 600-1-2); an immediate neighbour benefits from a favourable assessment, notably for loss of view or sunlight (CAA Versailles, 29 January 2026, No. 24VE03231).
  3. Notification of the challenge to the author of the decision and to the permit holder, by registered letter within fifteen clear days of filing, is a condition of admissibility with no possibility of regularisation (Article R. 600-1; CAA Bordeaux, 4 May 2023, No. 22BX00489).
  4. An urgent application for suspension requires urgency and a serious doubt (Article L. 521-1 of the Code of Administrative Justice); urgency is in principle presumed in planning matters (Article L. 600-3 of the Planning Code).

On the defence side, the court must examine whether the defects found can be regularised before suspending or annulling (CE, 16 June 2023, No. 470160): the stay of proceedings under Article L. 600-5-1 and the amending permit save most projects affected by partial defects.

Your documents

What to send according to your role

The report of the site notice, dated to the first day, is the key document for the timetable.

Position A

Neighbour or association

  • Permit decision and report of the site notice by a bailiff (commissaire de justice)
  • Project plans and extract of the local urban plan
  • Photos of the neighbourhood before and after the works, plan of the plots
  • For an association: articles of association filed at the prefecture at least one year before the applicant's application was posted at the town hall, and receipt for the registration declaration

Position B

Permit holder

  • Application file and plans as filed
  • Investigation report and opinions of the consulted departments
  • Letters exchanged with the town hall
  • Copy and proof of continuous posting (reports at the start and end)

Frequent mistakes: not having the posting recorded from the first day; a statutory purpose that is too narrow for the association; acting as a co-owner without authorisation from the general meeting.

The firm also handles particular situations:

  • Co-owners' association
  • Prior informal administrative appeal
  • Amending permit
  • Withdrawal of the permit by the town hall

The method

How the firm supports you

Sorting defects that can be regularised from those that cannot shapes the entire strategy.

Step 1

First exchange and sending the file

Call or email, sending the permit decision, the report of the site notice and the plans. First legal review within 24 to 48 hours.

Step 2

Review of standing and grounds

Standing, review of the file consulted at the town hall, comparison with the PLU, sorting of procedural, formal and substantive defects.

Step 3

Challenge before the administrative court

Drafting and filing of the application, registered notification to the town hall and to the permit holder within fifteen days, follow-up of acknowledgements of receipt.

Step 4

Urgent application for suspension and main proceedings

Parallel urgent application where there is urgency, further submissions, oral argument on the merits, follow-up of the appeal before the Paris Administrative Court of Appeal.

For the permit holder: defence submissions, request for a stay of proceedings under Article L. 600-5-1 and amending permit within the time limit set by the court.

The timetable

The timeline of a challenge in practice

The typical stages of a neighbour's challenge to a permit.

  1. Posting

    Day 0. First day of the continuous two-month period of posting required by Article R. 600-2.

  2. Bailiff's report

    Day +5. Report dated to the first day of posting, photographs of the sign and of the site.

  3. Consultation at the town hall

    Day +10. Reading of the application file, plans and opinions; identification of potential defects against the PLU.

  4. Challenge before the court

    Day +45 to +60. Filing of the application with the Paris administrative court within the two-month period; a prior informal administrative appeal is possible and suspends the period.

  5. R. 600-1 notification

    Day +45 to +75. Registered letter to the author of the decision and to the permit holder within fifteen clear days of filing: a condition of admissibility.

  6. Day +60 and beyond

    Possible urgent application for suspension, exchange of submissions, hearing on the merits, judgment, possible appeal.

The checks

What the firm checks before acting

No challenge without having validated these points.

  • Regularity of the posting: date of the first day, continuity over two months, legibility, content compliant with Article R. 424-15.
  • Standing: immediate neighbourhood, loss of view or sunlight, nuisance; for an association, the date and purpose of its articles of association.
  • Strength of the grounds: comparison of the file with the PLU, procedural, formal and substantive defects.
  • Sorting defects that can be regularised (amending permit possible) from those that cannot.
  • Timetable: dating of the filing, notification within fifteen days, follow-up of acknowledgements of receipt.
  • For the permit holder: proof of continuous posting and regularisation strategy.

Summary

Situation, evidence, time limit, action

The most frequent configurations at the firm, to quickly calibrate the priority and the procedural tool.

Situation

Permit posted at a neighbour's property

Decisive evidence: Bailiff's report dated to the first day, photos, extract of the PLU.

Time limit: 2 months from the first day of continuous posting.

Useful action: Action for annulment for excess of power (recours pour excès de pouvoir) before the Paris administrative court, R. 600-1 notification within 15 days.

Situation

Works already under way, urgency

Decisive evidence: Photos of the site, plans as filed, apparent defects against the PLU.

Time limit: At the same time as the application on the merits.

Useful action: Urgent application for suspension under Article L. 521-1 of the Code of Administrative Justice, urgency presumed, serious doubt.

Situation

Incomplete or non-compliant posting

Decisive evidence: Bailiff's report on the incomplete content of the posting.

Time limit: The period for challenge has not yet started.

Useful action: Challenge only after two months of regular posting, or direct challenge.

Situation

Permit holder challenged before the administrative court

Decisive evidence: Application file, investigation, plans, opinions of the departments.

Time limit: Time allowed by the court for observations (15 to 30 days).

Useful action: Defence submissions, request for regularisation under Article L. 600-5-1 if there is a defect.

Situation

Partial defect in the permit

Decisive evidence: Identification of the defect, amended plans ready, agreement of the town hall.

Time limit: Time set by the court in the stay of proceedings.

Useful action: Regularising amending permit, communicated to the court within the time limit.

Situation

Withdrawal of the permit by the town hall

Decisive evidence: Withdrawal decision, reasons given, 3-month period elapsed.

Time limit: 2 months after notification of the withdrawal.

Useful action: Challenge by the permit holder, argument on the lawfulness of the original permit.

The firm's practical cases

Anonymised examples. The figures correspond to real cases, rounded for discretion.

The anonymised examples below illustrate the variety of situations handled. The figures correspond to real cases but have been rounded for discretion.

Permit annulled for lack of a prior public inquiry

Plot of 600 square metres in a protected zone, industrial extension project. Challenge by neighbours and an environmental association. The administrative court annulled the permit, noting the absence of a public inquiry that was nevertheless required. The permit holder abandoned the project and redirected the investment.

Action: action for annulment. Result: permit annulled, project abandoned.

Neighbour did not notify within 15 days, challenge inadmissible

A neighbour challenging a residential permit filed the challenge within the two-month period, but notification to the permit holder was sent on the 18th day, outside the R. 600-1 time limit. The court dismissed the challenge as inadmissible. The project was able to proceed without delay.

Action: defence of the permit holder. Result: challenge inadmissible, project secured.

Regularisation by amending permit, project saved

Roof extension project of approximately 80 square metres challenged by neighbours for marginally exceeding the building envelope set by the PLU. The court stayed proceedings under L. 600-5-1, and an amending permit correcting the height was filed. The project was saved, avoiding a demolition cost estimated at €280,000.

Action: regularisation under L. 600-5-1. Result: project maintained after correction.

Frequently asked questions

Your questions: building permit challenges

How long do you have to challenge a building permit?

The time limit to apply to the administrative court (tribunal administratif) is two months from the first day of a continuous two-month period during which the permit is posted on the site, in accordance with Article R. 600-2 of the Planning Code (Code de l'urbanisme). Before regular posting, the period does not run, which leaves the permit holder in a period of uncertainty. Once the two months of continuous posting have elapsed, the period runs against third parties, and any application filed after it is inadmissible. Beyond the strict time limit for litigation, Article R. 600-1 of the Planning Code requires the challenge to be notified to the author of the decision and to the permit holder within fifteen clear days of filing, on pain of inadmissibility. The timetable is therefore tight: you must act quickly once the posting is noticed, have a bailiff's report drawn up, consult the file at the town hall and prepare the challenge.

Who can challenge a building permit in France?

Article L. 600-1-2 of the Planning Code makes standing a condition of admissibility. The following are admissible: the immediate neighbour whose conditions of occupation, use or enjoyment of the property are directly affected by the project, and the co-owners' association (syndicat des copropriétaires) where the neighbouring project affects the common parts. The State, local authorities, their groupings and associations are not subject to this condition; associations fall under Article L. 600-1-1. The immediate neighbour benefits from a favourable presumption, but must produce concrete evidence of loss of view, sunlight and nuisance. The Versailles Administrative Court of Appeal recalled this in a recent judgment, upholding the standing of a female neighbour who showed that her light and views were impaired (CAA Versailles, 29 January 2026, No. 24VE03231). The association must have filed its articles of association at the prefecture at least one year before the applicant's application was posted at the town hall (Article L. 600-1-1).

How do you notify a challenge under Article R. 600-1?

Notification must be made by registered letter with acknowledgement of receipt, within fifteen clear days of the filing of the challenge, in accordance with Article R. 600-1 of the Planning Code. Notification is deemed to have been made on the date of dispatch, as shown by the certificate of posting. It must be sent to two recipients: the author of the decision (town hall or prefect) and the holder of the authorisation (permit holder). Omitting either recipient makes the challenge inadmissible, and this can no longer be regularised once the time limit has expired. The Bordeaux Administrative Court of Appeal has recalled how strict this rule is (CAA Bordeaux, 4 May 2023, No. 22BX00489). The letter must contain a full copy of the challenge to be effective: a mere covering letter without a copy is insufficient.

Is an urgent application for suspension automatic?

No. The urgent application for suspension (référé suspension) provided for by Article L. 521-1 of the Code of Administrative Justice requires two conditions: urgency and a serious doubt as to the lawfulness of the act. For building and development permits, urgency is in principle presumed, because of the difficulty of reversing works. However, this presumption can be rebutted by the permit holder who shows that the works are not advanced or that they are reversible. The serious doubt must be established by the applicant: grounds of external lawfulness (lack of reasons, defective signature) or of internal lawfulness (non-compliance with the PLU, exceeding the building envelope). The Council of State (Conseil d'État) stated in a recent judgment that the court must verify whether the defects alleged can be regularised (CE, 16 June 2023, No. 470160). The urgent application is heard at a public hearing, as a rule within one month, and the order is issued within a short time.

Can the permit holder regularise a permit that is being challenged?

Yes. Article L. 600-5-1 of the Planning Code provides that where the administrative court finds that a defect affecting the contested decision is capable of being regularised, it stays proceedings after inviting the parties to submit their observations. The court sets a time limit for regularisation by an amending permit (permis modificatif). This mechanism, supplemented by Article L. 600-9 of the Planning Code, aims to save projects rather than annul them. The amending permit corrects only the unlawful aspects. The original permit remains in place for the rest, and the project can continue after regularisation. The permit holder's defence therefore systematically involves identifying the defects that can be regularised and preparing an amending permit at the same time. This procedural flexibility avoids outright annulments and demolition costs.

Can the town hall withdraw a permit it has just issued?

Yes, within three months of the decision and only if the permit is unlawful, in accordance with Article L. 424-5 of the Planning Code. Withdrawal requires precise reasons identifying the unlawfulness. After the three-month period, withdrawal is no longer possible and the permit becomes final as far as the administration is concerned: only the administrative court can then annul it, on a challenge by a third party. This rule protects the permit holder against reversals by the administration. The withdrawal must be notified to the beneficiary with details of the means of challenge and time limits. The permit holder has two months to challenge the withdrawal before the administrative court. The defence then concerns the lawfulness of the original permit: if the permit complied with the planning rules, the withdrawal is annulled and the permit regains its full effect. This procedure is strategic where the town hall has yielded to pressure from the municipality or from neighbours after the permit was issued.

Does a neighbour's challenge suspend the works?

Not automatically. An action for annulment for excess of power (recours pour excès de pouvoir) does not of itself suspend the decision. The beneficiary may continue the works even if a challenge is brought, until the court annuls or suspends the permit. To have the works stopped, the neighbour must file an urgent application for suspension alongside the application on the merits, under Article L. 521-1 of the Code of Administrative Justice. The urgent application is decided within a few weeks, on the conditions of urgency and serious doubt. Without an urgent application for suspension, the works may be completed before judgment on the merits, which complicates restoration. This is why the urgent application for suspension is the neighbours' decisive weapon: it freezes the situation while the main proceedings are under way. For the permit holder, urgency means defending the urgent application and the merits at the same time, and anticipating the possible regularisation of the defects identified.

Which court has jurisdiction over a building permit challenge in Paris?

The Paris administrative court has jurisdiction over challenges to building permits issued by the City of Paris, in accordance with Article R. 312-1 of the Code of Administrative Justice. Territorial jurisdiction follows the place where the contested decision was made. The Paris administrative court has a chamber specialised in planning law that handles all Paris challenges. Representation by a lawyer is not mandatory at first instance for an action for annulment for excess of power, but it is very strongly recommended, and it is mandatory on appeal. The appeal is brought before the Paris Administrative Court of Appeal within two months of service of the judgment. An appeal on points of law to the Council of State is then available within two months, but is filtered by an admission procedure. For permits issued in the other départements of the Paris region (Île-de-France), the administrative court of Versailles, Cergy or Melun has jurisdiction depending on the municipality.

Can you challenge a permit without owning the property?

Yes, subject to conditions. Article L. 600-1-2 of the Planning Code opens the action to any person whose conditions of occupation, use or enjoyment of the property that they own or regularly occupy are directly affected. A tenant of a flat, a usufructuary or an occupant who pays no rent, with the owner's permission may therefore bring a challenge. Proof of standing rests on the lease, the marriage certificate, a certificate of residence, or any document establishing regular occupation. The condition remains that the contested project directly affects the conditions of occupation: light, view, quiet, rental value. An occasional or passing occupant is not admissible. The administrative case law applies this condition strictly, in order to reject dilatory challenges based on a mere occasional presence.

What defects can lead to a permit being annulled?

Defects fall into two categories: external lawfulness and internal lawfulness. External lawfulness covers defects of competence (signature by a person without authority), of procedure (failure to consult the departmental commission, absence of a public inquiry) and of form (lack of reasons, defective signature). Internal lawfulness covers non-compliance with planning rules: breach of the PLU (building envelope, footprint, height, land-use coefficient (COS)), breach of public-utility easements, harm to the environment, breach of set-back rules, failure of landscape integration. Not all defects are equal. Some can be regularised by an amending permit under Article L. 600-5-1 of the Planning Code: an excess of building envelope can be corrected, a failure to consult can be cured. Others are irreparable: non-compliance with a zoning rule that purely and simply prohibits the construction. The strategy rests on identifying the defects and ranking them.

Can a tacit permit be challenged?

Yes. A tacit permit, which results from the administration's silence beyond the examination period, can be challenged under the same conditions as an express permit. The two-month period for litigation runs from the first day of a continuous two-month period of posting on the site, the posting being the responsibility of the beneficiary. Proof of the tacit permit rests on the receipt for filing of the application and the absence of a decision within the period. The neighbour may ask the town hall for a certificate stating that no express decision has been taken and that the permit is deemed granted. Tacit permit litigation presents a particular difficulty: since the decision has no express reasons, the applicant must base the grounds solely on internal lawfulness, that is, the project's compliance with the applicable planning rules. Grounds of procedure or form are generally ineffective against a tacit permit, except where the mayor lacked competence to issue a tacit authorisation in the case at hand.

How much does a building permit challenge cost?

The cost depends on the complexity of the case. There are three main items: lawyer's fees, the cost of any expert assessment, and court costs (dépens). Lawyer's fees are generally between €4,000 and €12,000 for a full procedure (challenge on the merits with submissions, possible urgent application for suspension, oral argument), depending on whether the challenge is individual or collective. Expert assessment costs are rare in planning matters: most cases are dealt with on the documents, without a court-appointed expert assessment. Court costs (procedural costs) are fixed at the end of the proceedings and include copies and, where relevant, the bailiff's report. If successful, the court may order the losing party to pay the costs and a sum under Article L. 761-1 of the Code of Administrative Justice, generally between €1,500 and €5,000. For a co-ownership or a group of neighbours, sharing the costs reduces the individual cost. The firm prepares a detailed quote at the start of the case, including the split between neighbours where the action is collective, and proposes a clear funding arrangement before any filing.

A building permit under challenge? Act today.

Whether you are a neighbour, an association or a permit holder, the two-month period often decides the outcome of the case. Send the permit decision, the report of the site notice and the plans: the firm replies within 24 to 48 hours.

The latest news.

What our clients say

4,9289 Google reviews
kader ladjouzi
1 month ago

Best real estate law and business law lawyer in Paris. A humane and attentive lawyer, with a wonderful team. Thank you, Maître KOHEN

Translated from French

Janou SAMUEL
2 months ago

Thank you to Maître KOHEN for his analyses of recent case law on fraudulent non-disclosure in property sales. It reassures me about an action for annulment that I am considering after buying a house affected by serious defects intentionally concealed by the seller and not reported by the estate agent; also defects (rising damp) characterised by spreading through-cracks and damp stains, not reported by the estate agent… Worse, defects concealed by the latter or at his instigation, under a coat of paint and by polystyrene tiles glued to the ceiling of a bedroom. And the said estate agent drafted the preliminary contract, which of course contains no information about any of these defects. Just to add that, being 77 years old and suffering from cognitive impairment, I am certain that the estate agent thought I would not be able to discover the deception and above all to establish the fraudulent intent, still less to bring legal proceedings given the complexity and length of the procedure... That is why I am opting for the criminal route, insofar as the intentional concealment of the defects by the seller and then by the estate agent amounts to the fraudulent manoeuvres of art. 313-1 of

Translated from French

Paul MALIK (powlo)
5 months ago

Maître Reda KOHEN assisted me in a dispute concerning a sale agreement with a defaulting party. He provided professional and responsive support, and I highly recommend him.

Translated from French

Rayan Kallout
6 months ago

I highly recommend Maître Reda Kohen. Thanks to his explanations, I was able to recover my security deposit in a situation that seemed blocked. He was responsive, clear, and very professional. A big thank you for his invaluable help!

Translated from French

Naji Jouahri
6 months ago

Excellent support from Maître Kohen in a case combining business law and real estate law. Clear legal analysis from the first meeting, right through to the hearing. Professional and accessible lawyer, I highly recommend his firm in Paris 17.

Translated from French

Halim Tunde
6 months ago

Maître Kohen assisted me in recovering unpaid debts from a defaulting tenant. Procedure mastered from start to finish, from the payment order to eviction. Human, attentive, and always reachable. Thank you for your work.

Translated from French

Cha
6 months ago

As a young student living in an apartment, my landlord tried to make me leave my accommodation even though he had sent me no termination notice. I therefore contacted Mr. Reda Kohen to help me as I couldn’t handle the situation alone. In just 3 days everything was resolved, Maître Kohen defended me and accompanied me with an irreproachable level of commitment and efficiency. I can only recommend his professionalism!

Translated from French

Asmaa Maazaz
7 months ago

I turned to Maître Kohen for a complex real estate dispute and I highly recommend his firm. He is very professional; he thoroughly analyzed my case from the very first appointment and clearly explained the possible options. Thanks to his expertise, we achieved a very favorable outcome. Responsive, a good teacher, and committed, he is a lawyer you can truly trust. Yours faithfully, Miss Maazaz

Translated from French

Contact Mobile
6 days ago

Very satisfied! I would like to thank Maître Esther Cornu here, who managed to resolve a very complicated dispute in a divorce and family law matter...Thanks to Maître Cornu, a judgment was handed down in my favour even though it was far from a foregone conclusion...So I recommend this law firm

Translated from French

Claude Frasson
1 week ago

A precise and concrete analysis and an immediate response. Excellent.

Translated from French

Basel Alali
1 week ago

I highly recommend this lawyer for his professionalism, honesty, and transparency. He helped me successfully and guided me through the process with great care and expertise. What I particularly appreciated was his honest approach and the fact that he recommended practical, cost-effective options instead of immediately pushing for the most expensive solution. He genuinely focused on finding the right approach for my situation. I’m very grateful for his support and would definitely recommend him to anyone looking for a trustworthy and professional lawyer in France.

beatrice lefevre
1 week ago

Thank you for this detailed, precise help, with a proposal at the end on whether or not to continue (very quick response as well)

Translated from French

Jean-pierre Steinmetz
2 weeks ago

Very good advice given by Maître Cornu during our meeting on 16 October.

Translated from French

John Roberts
2 weeks ago

Very professional and responsive service. The lawyer quickly and carefully checked the validity of my wife’s residence permit in light of a specific legal regime. His work gave us clarity, whereas the usual administrative procedures were long and ambiguous. I appreciated his efficiency and professionalism, and I recommend his services.

Translated from French

Jean-François PAPA
3 weeks ago

I would like to warmly thank Maître Esther Cornu for her professionalism, her availability and the quality of her support. In a case of particular importance for my professional future, she showed great responsiveness, rigour and a gift for explaining things, taking the time to answer my questions precisely and to explain the various legal steps to me. I particularly appreciate the clarity of her analyses, her seriousness and her commitment in following up my case. Many thanks to Maître Esther Cornu for listening and for her support. I highly recommend!

Translated from French

Hamid Agouz
3 weeks ago

I was pleasantly surprised by the responsiveness of Mr Reda Cohen, who took the time to answer my questions about my case instantly. It has become so rare these days to find a lawyer who is so available, responsive and attentive, even when it is simply a matter of answering questions. His answers are clear, precise and reassuring. You can tell that he takes the time to understand the situation and to provide relevant answers. Beyond his excellent ratings on Google, it is above all this availability and this seriousness that make the difference. Many thanks to Mr Reda Cohen for his professionalism and his responsiveness. I highly recommend!

Translated from French

Sandra Imbert
3 weeks ago

A huge thank you to Maître Esther Cornu from Kohen Avocats for her support during a particularly difficult time. Her attentiveness, empathy, and humanity touched me deeply. She was able to answer my questions with clarity and sensitivity, while demonstrating great professionalism and fully respecting the confidentiality of the case. Beyond her professional qualities, I met a deeply humane lawyer whose support made a real difference. I sincerely recommend her.

Translated from French

Мария Двирник
1 week ago
Moula Brahimi
1 week ago

Good experience. And good work, thank you for everything.

Translated from French

Faiza Traduction
1 week ago
Alain Arsaut
2 weeks ago

Saw Hassan on the TV news

Translated from French

Beaudrique Abao
2 weeks ago
Krep Events Traiteur Breton
3 weeks ago

very clear article

Translated from French

TOULEIMAT HACHEM
3 weeks ago